
.png)
APRIL 15
BREAKOUT SESSION #2
3:30 PM
Fairway Left Room
1 DBIA Credit Hour
1 AIA Credit Hour
The State of Oklahoma adopted enabling legislation for Design Build project delivery of water and wastewater treatment systems in 2021. This legislative change included a pilot program for ODEQ to develop and then promulgate rules for the new flexible permitting process. The timing of this legislative change aligned with Tulsa Ports’ development of a master plan for their Inola Industrial Park that included a new wastewater treatment plant. The South Inola WWTF was subsequently submitted and adopted as one of the ODEQ flexible permitting pilot projects.
The learning curve of a new process with the local regulatory body is not to be underestimated. Their codes and processes have been developed over decades around traditional hard bid projects, and these processes are well ingrained into the agencies. This presents a challenge, but it is not insurmountable. In fact, it is a challenge that is easily overcome with the same collaboration skills that make progressive design build projects effective.
Effective collaboration with regulatory agencies includes early engagement, creative problem solving, and regular communication. The project worked closely with ODEQ beginning with the conceptual design to advise how the project was going to be packaged for review, purchasing, and construction. While there were still challenges, this early communication aided in the approval process. The development of the package approach was informed by ODEQ’s constraints and concerns, to further support partnership and collaboration on the project.
This presentation will review the collaborative approach, the challenges that were encountered between legislation and administrative code, and the final package breakdown that was presented to ODEQ for permitting approval. It will conclude with a discussion on potential next steps to improve collaboration and alignment with regulatory codes and legal requirements.
Learning Objectives:
The progressive design build approach is an innovative delivery method to the Oklahoma water/wastewater sector and the pilot program has presented an opportunity for design-build best practices to be incorporated into the permitting rules.
To successfully deliver design-build projects, collaboration must extend beyond the project team and include the regulatory and permitting authorities.
As design build legislation is enacted, implementation of design build projects may conflict with existing codes or processes and will require creative problem solving as new processes are developed. The project team’s understanding of these regulatory challenges is key to success.
Design packages and work packages should be planned to align with regulatory processes in order to streamline approvals.
Sponsored by
